Project Background and Requirements

A large chemical enterprise's reactor temperature monitoring project required simultaneous monitoring of temperature at 6 different heights within a single reactor to precisely control the reaction process. Traditional single-point thermometers cannot meet the demand for multi-point synchronous measurement, and wiring is complex with high maintenance costs.

The customer required the multi-point thermometer to have high precision, fast response, and corrosion resistance, and to be able to connect to the existing DCS system. After on-site investigation, the project team determined a customized multi-point thermometer solution.

Multi-point thermometer project on-site installation video

Key Points for Multi-Point Thermometer Selection

Comparison of Key Parameters

Parameter Option A (Sheathed PT100) Option B (Thermocouple) Option C (Digital Sensor)
Accuracy ±0.1℃ ±1.5℃ ±0.5℃
Response Time ≤10s ≤5s ≤15s
Corrosion Resistance Excellent (316L sheath) Moderate (requires protective sleeve) Good (PTFE coating)
Wiring Complexity Moderate (three-wire) High (compensation wire) Low (bus)

Considering accuracy, corrosion resistance, and DCS compatibility comprehensively, Option A (sheathed PT100 multi-point thermometer) was finally selected.

Implementation Steps

Installation and Commissioning Process

  1. On-site Surveying: Determine the height and insertion depth of each temperature measurement point, and customize flange dimensions.
  2. Sensor Assembly: Weld 6 PT100 sheathed elements at intervals within a unified protective sheath, and fill with thermal conductive silicone grease.
  3. Installation and Fixation: Vertically insert the multi-point thermometer into the reactor through the flange, ensuring each measurement point is at the target position.
  4. Wiring and Configuration: Connect to the temperature transmitter using a three-wire connection, and configure the range and alarm values in the DCS.
  5. Calibration and Verification: Perform three-point calibration for each measurement point using a dry block calibrator, with errors all less than ±0.2℃.
Multi-point thermometer commissioning process

Project Results and Benefits

  • Improved Temperature Measurement Efficiency: Single-point inspection time reduced from 15 minutes to 2 minutes, achieving real-time multi-point monitoring.
  • Enhanced Reliability: The sheathed structure withstands 16MPa pressure and has operated continuously for 12 months without failure.
  • Cost Savings: Compared to 6 single-point thermometers, installation materials and wiring costs are saved by approximately 35%.
  • Data Integration: All temperature signals are directly connected to the DCS and participate in interlock control, improving reaction safety.

This project verified the applicability of multi-point thermometers in complex industrial environments, providing a reliable temperature measurement solution for similar reactors, storage tanks, pipelines, and other scenarios.

Selection and Procurement Recommendations

  • Clarify the number of temperature measurement points, spacing, and insertion depth, and prioritize customized sheathed structures.
  • Select sheath material (such as 316L, Hastelloy) based on medium corrosiveness.
  • Confirm that the output signal type (RTD, 4-20mA, HART, etc.) matches the control system.
  • Require the supplier to provide single-point calibration reports and third-party metrology certification.

For more multi-point thermometer application cases or technical parameters, please contact us for detailed information.