B 61-300 Chinese Manual Overview
The B 61-300 is a pressure instrument widely used in industrial process control. This Chinese manual provides complete technical information for engineering technicians and procurement personnel. Through this article, you can quickly understand its core parameters, installation specifications, and maintenance methods.
Download B 61-300 Chinese Manual.pdf
Main Technical Parameters
The key performance indicators of the B 61-300 are shown in the table below. When selecting a model, be sure to confirm that the on-site working conditions match the parameters.
| Parameter | Specification |
|---|---|
| Measurement Range | 0~1.6 MPa (customizable) |
| Accuracy Class | ±0.5% FS |
| Operating Voltage | 24 V DC |
| Output Signal | 4~20 mA |
| Process Connection | M20×1.5 external thread |
| Protection Rating | IP65 |
Installation and Wiring Steps
Correct installation and wiring are the foundation for ensuring the long-term stable operation of the B 61-300. Please follow the steps below:
- Confirm that the pressure in the pipeline has been released and close the shut-off valve.
- Screw the instrument process connection into the pipeline interface and tighten it with a wrench, avoiding excessive force.
- Connect the power and signal lines according to the wiring diagram in the manual, paying attention to polarity.
- After power-on, check whether the output current is normal and perform zero calibration if necessary.
Wiring Precautions
- Use shielded cables and ground them at one end.
- Avoid laying cables parallel to power cables.
- Ensure the supply voltage is within the range of 24 V DC ±10%.
Calibration and Maintenance Points
Regular calibration can maintain the measurement accuracy of the B 61-300. It is recommended to calibrate once every 12 months.
- Zero Calibration: Under no pressure, adjust the zero potentiometer so that the output is 4 mA.
- Full-Scale Calibration: Apply full-scale pressure and adjust the span potentiometer so that the output is 20 mA.
- When cleaning, use a soft cloth dipped in neutral detergent and avoid corrosive solvents.
- If reading drift or abnormal output is found, first check the wiring and power supply.
Common Questions and Selection Recommendations
When purchasing the B 61-300, please choose the appropriate model according to the actual medium temperature, pressure range, and explosion-proof requirements. Common questions include:
- No output signal: Check the power supply and polarity.
- Large reading deviation: Recalibrate or check whether the process connection is leaking.
- Display fluctuation: Confirm whether the medium is pulsating and install a damper if necessary.
For complete technical information, please download the B 61-300 Chinese Manual.pdf above.